(Hanoi, Bloomberg) Vietnam may be forced to delay the start of operations at its first nuclear power plants until after 2035.

In a draft revision of the National Power Development Plan released this week for consultation, Vietnam’s Ministry of Industry and Trade proposed that the Ninh Thuan 1 nuclear power plant begin operations in 2037 or 2038, and Ninh Thuan 2 in 2039 or 2040.

Vietnam Electricity Group (EVN) has submitted a pre-feasibility study for the Ninh Thuan 1 nuclear power plant to the Ministry of Finance. Under the existing plan, the plant is due to begin operations between 2030 and 2035. However, the project’s planners, including partner Rosatom, estimate that it will take at least 12 years from the completion of the feasibility study to finish building the plant.

Vietnam Electricity Group nevertheless proposed bringing completion forward to 2034 or 2035 if conditions permit. The Ninh Thuan 2 nuclear power plant, being jointly developed by Petrovietnam and South Korean partners, could be completed in 2035 or 2036 at the earliest.

BloombergNEF analyst Phan Hanh warned: “Setting shorter and ambitious timelines for expensive and emerging technologies such as nuclear power can increase the risk of shortfall in future power-generation capacity.”

The potential delays to the nuclear projects cast a shadow over Vietnam’s efforts to develop nuclear power to reduce its reliance on imported fossil fuels.

The revised power development plan also pushes back construction schedules for liquefied natural gas (LNG) power projects. Vietnam’s installed LNG-fired power generation capacity is expected to reach about 4.3 gigawatts by 2030, less than half the target under the existing plan.

Vietnam’s Ministry of Industry and Trade said last month that only one of the country’s 18 planned LNG power projects was on schedule, and construction had begun on just two.