(Washington, agencies) US President Donald J. Trump has threatened to impose heavy taxes on US companies building artificial intelligence (AI) data centres overseas. His remarks highlight a divide between him and the public: Trump sees expanding domestic data centre construction as crucial to winning the technology race, but the public is deeply sceptical about the benefits these facilities can bring.

Speaking at a White House press conference on Friday (20 November), Trump warned that the US could lose its lead if a growing political backlash slowed data centre construction.

He said: “We’re not going to allow companies to build data centers in other countries. If they do that, they can. But we’re going to put a tremendous tax on them.”

Several major US data centre operators, including Equinix and Digital Realty, currently build and operate facilities overseas. Operators typically locate facilities close to their customers to reduce data transmission times and avoid delays in time-sensitive operations such as payments. This also avoids the high cost of transmitting vast amounts of data over long distances.

Trump wants to prevent data centres from moving overseas, but an Associated Press survey found that about three-quarters of US voters oppose building them in their own communities. Most Americans are very concerned that data centres could drive up local electricity bills or affect community water supplies.

Addressing these concerns, Trump urged communities to negotiate benefits from technology companies seeking to build data centres. “And you want to take advantage of the data centers. Make them pay you. Make them pay your community……Don’t shut them off.”

Surging demand for AI computing power has driven up the cost of building large data centres. A report by project management company Turner & Townsend found that data centre construction costs rose 13% this year, more than twice the global rate and about three times the average increase over the past decade.

The report examined more than 500 data centre projects under construction or recently completed across 62 markets worldwide, and gathered views from 400 data centre industry experts around the world.

Turner & Townsend’s Paul Barry, North America data center lead, explained that sharply compressed project schedules were prompting contractors and subcontractors to raise their bids. These include charges for accelerated work, overtime and recruitment incentives, as well as additional fees for taking on project delivery risks far beyond the norm.

Power is essential to data centres. According to the report, 56% of industry respondents viewed power supply issues as the main obstacle to getting projects off the ground. Labour shortages are another major constraint, with only just over a quarter of respondents saying their contractors had enough capacity to handle their backlog of projects under construction.

Looking ahead to next year, Barry expects data centre construction cost increases to ease to between 6% and 10%.